GENKO installation and integration

The installation must preserve a representative sample and an interpretable record.

Sampling and utilities

Define the sampling point, sample route, power supply, panel location, return or drain and cleaning conditions. Detailed engineering is reviewed with the operating team.

Data and communication

Available interfaces and records must be confirmed for the proposed version. The review must identify the PLC, web interface and OPC UA connection to SCADA when they form part of that configuration.

Records for diagnosis

Retain the date, sample identification, measurement mode, cycle states and test conditions. Agree on units, synchronisation and quality before incorporating the record into the historian.

Commissioning

Verify sampling, the cycle, sample return, instruments and records. Compare with a reference method and agree on acceptance criteria; do not apply universal tolerances without data.